Mali approves $190m Bamako power grid project backed by AfDB

Mali's transitional parliament approved financing agreements for the $190 million Bamako North 225 kV Loop Project, Daba Finance reported on 7 July 2026. Funding includes a $35.27 million African Development Fund loan, $18.99 million from the AfDB's Transition Support Facility, Climate Investment Fund and Green Climate Fund money, and contributions from the West African Development Bank, the Islamic Development Bank and the government. The project adds a 225 kV line, new substations at Safo and Kénié, and aims to connect 10,000 households and small businesses and improve supply to about 40 industrial sites, with construction expected to start in the third quarter of 2026.

Why it matters

A stronger Bamako grid targets the power cuts that hold back industry in Mali's main economic centre.

Source: Daba Finance (via AllAfrica) · 7 July 2026