BOLDEN African News · Monday 9 November 2026
PhosCo puts the initial cost of its Gasaat phosphate mine in Tunisia at $199 million
Australian miner PhosCo released an updated preliminary economic assessment of its Gasaat phosphate project in Tunisia, raising the initial capital estimate to $199 million from $169.5 million. The study plans 1.4 million tonnes of phosphate concentrate a year over 49 years, with an after-tax NPV of $732 million, an after-tax IRR of 52% and a 20-month payback. The EBRD has made a structured investment of A$7.5 million ($5.1 million) to fund the next study phase, a pre-feasibility study.
Why it matters
It is a foreign-led attempt to develop new phosphate supply in Tunisia, where the sector is dominated by the state.
Source: Ecofin Agency · 9 November 2026