EBRD and the Clean Technology Fund finance STEG's 50MW solar plant with battery storage in Tataouine

Tunisia and the EBRD signed agreements on 11 November for a €50 million (nearly 167 million dinars) STEG project at Beni Mhira, Tataouine: a 50MW solar plant with a 10MW battery storage system, described as Tunisia's first. The EBRD lends €30 million at 1% and the Clean Technology Fund €20 million at 0.62%, over 18 years with a five-year grace period, plus a €4 million technical assistance grant. Works are due to start in the first quarter of 2027, with commissioning planned for summer 2028.

Why it matters

It is the first grid battery storage at Tunisia's public utility, a test case for how STEG takes on more solar.

Source: Business News (Tunisia) · 12 November 2026