Resolute Mining considers a second processing plant at its $516 million Doropo gold project
In a presentation on 11 November, Resolute Mining said it is considering a second gold processing plant at Doropo in Côte d'Ivoire, to treat ore from the Kilosegui deposit about 30 km from the plant now under construction. Kilosegui holds reserves of 856,000 oz, about 34% of Doropo's roughly 2.5 million oz, and a 20,000-metre drilling programme is under way. The approved $516 million project is designed to produce an average of 169,000 oz a year over 13 years, with first gold targeted for the first half of 2028; the second plant is not yet approved.
Why it matters
A second plant would extend one of Côte d'Ivoire's largest new gold mines as the country builds up its gold sector.